A team is trying to convince a customer about the value of adopting Scrum. The customer likes some of the features of the methodology like the bi-weekly demonstration, but the customer remains largely unconvinced of the value of Scrum and refuses to change the way of working,
What should the team do?
Correct Answer:
C
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?
Correct Answer:
A
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
Correct Answer:
B
A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8.
What is this technique called?
Correct Answer:
C
What is the relationship between the Product Backlog, the Release Backlog and the Sprint Backlog?
Correct Answer:
C